- Access and traffic.
- Prior to any filling activity, all on-site roads used in the fill operation and all roads from the site to a public right-of-way shall be designed and constructed to accommodate the vehicles and equipment which will use them.
- All on-site and private access roads shall be paved or adequately maintained to minimize dust and mud generation within 100 feet of a public right-of-way.
- No material shall be tracked or discharged in any manner onto any public right-of-way.
- The applicant shall submit a traffic management plan that identifies impacts to existing County infrastructure and an assessment as to the ability of the existing infrastructure to withstand increased traffic loading and usage. The County Engineer shall review the submitted plan and shall certify, based on findings relating to the Multnomah County Rules for Street Standards, that the road(s) identified in the plan:
- Are suitable for all additional traffic created by the fill operation for the duration of the activity, or
- If the roads are unsuitable for all additional traffic created by the fill operation for the duration of the activity that:
- The applicant has committed to finance installation of the necessary improvements under the provisions of 02.200(a) or (b) of the Multnomah County Rules for Street Standards, and
- A program has been developed for the number and weight of trucks that can safely be accommodated at specific levels of road improvement. Based upon those findings, the Hearing Authority may attach related conditions and restrictions to the conditional use approval.
- Truck movements related to the dumping of materials shall occur entirely on-site and not utilize the public right-of-way or private easements.
- Proposals in proximity to state highway facilities need to be reviewed by the Oregon Department of Transportation.
- Buffer requirements.
- All existing vegetation and topographic features which would provide screening and which are within 100 feet of the proposed area of fill shall be preserved. The applicant shall demonstrate that the existing screening is sufficient to ensure the project site will not noticeably contrast with the surrounding landscape, as viewed from an identified viewing areas, neighboring properties, or accessways, or;
- If existing vegetation and topography is insufficient to obscure the site from neighboring properties, accessways or identified key viewing areas, the applicant shall propose methods of screening and indicate them on a site plan. Examples of screening methods include landscape berms, hedges, trees, walls, fences or similar features. All required screening shall be in place prior to commencement of the fill activities.
- The Approval Authority may grant exceptions to the screening requirements if:
- The proposed fill area, including truck line-up area and fill areas are not visible from any neighboring properties, key viewing areas and accessways identified in (b) above, or
- Screening will be ineffective because of the topographic location of the site with respect to surrounding properties.
- Signing.
One directional sign for each point of access to each differently named improved street may be allowed for any operation. Signing shall be specified and controlled by the standards of MCC 11.15.7974.
- Timing of Operation
- Hours of operation shall be specified on each application. At a maximum operating hours shall be allowed from 7:00 am to 6:00 pm. Large fills shall not operate on Sundays or on New Year’s Day, Memorial Day, July 4th, Labor Day, Thanksgiving Day, and Christmas Day.
- The placement of fill materials shall not occur from October 1st - May 1st .
- Air, water, and noise quality.
- The applicant shall obtain and comply with the standards of all applicable permits from the Department of Environmental Quality. Copies of all required permits shall be provided to Multnomah County prior to beginning filling. If no permits are required, the application shall provide written conformation of that from the Department of Environmental Quality.
- Sound generated by an operation shall comply with the noise control standards of the Department of Environmental Quality. Compliance with the standards may be demonstrated by the report of a certified engineer.
- Minimum Setbacks.
- For filling activities the minimum setback shall be 100 feet to a property line, or if multiple parcels, to the outermost property line of the site.
- For access roads and residences located on the same parcel as the filling or processing activity, setbacks shall be as required by the underlying district.
- Reclaimed Topography.
All final reclaimed surfaces shall be stabilized by ground control methods as specified by the landscape architect. Reclaimed surfaces shall conform with the natural landforms of the surrounding terrain.
- Safety and security.
Safety and security measures, including fencing, gates, signing, lighting, or similar measures, shall be provided to prevent public trespass and minimize injury in the event of trespass to identified hazardous areas such as steep slopes, water impoundments, or other similar hazards .
- Phasing program.
Each phase of the operation shall be reclaimed within the time frame specified in subsection (11) or as modified in the decision.
- Timeline
Timelines for Large fill Conditional Use Permits shall conform with the 2-year period pursuant to MCC 11.15.7110(C), unless otherwise approved by the Approval Authority. The applicant may request a longer time period for completion as part of the initial application. If an approval has been issued, the applicant may request a longer time period for completion pursuant to MCC 11.15.8240 (E).
If completion of a large fill project extends beyond 2 years pursuant to MCC 11.15.7110(C), the applicant shall submit an engineering report prepared and signed by a licensed engineer at least once per year by October 31, or as otherwise specified by the Approval Authority. The engineering report shall describe at a minimum the following:
- The amount of fill added to the site since the start of the fill or the last engineering report and stability measures used and planned for the new fill.
- Future fill locations within the approved site and stability measures planned both within and outside the fill site.
- incidents of landslide or other instability within and outside the fill site, clean-up efforts for these incidents, and measures used and planned to prevent future incidents.